[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-349530":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},349530,141,2,"多选题","在进度控制中，应关注材料、设备的供应情况，其中特别值得重视的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","各项设备是否完成",true,{"key":16,"text":17,"correct":14},"B","计划运到日期",{"key":19,"text":20,"correct":14},"C","各种材料的供货厂商是否落实",{"key":22,"text":23,"correct":14},"D","材料设备交货时间",{"key":25,"text":26,"correct":27},"E","材料设备成本",false,"ABCD","考点:进度控制。影响工程进度的因素很多，需要特别重视的方面之一是材料、设备的供应情况，包括各项设备是否完成，计划运到日期；各种材料的供货厂商是否落实，何时交货，检验及验收办法等。",{"id":6,"name":31,"category":32,"favorite":33},"开发经营与管理","职业资格",0]