[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-349529":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},349529,141,2,"多选题","在工程项目施工阶段，质量控制的任务主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定质量控制的对象",false,{"key":16,"text":17,"correct":18},"B","对所选用的材料和设备进行质量评价",true,{"key":20,"text":21,"correct":18},"C","对整个施工过程中的工程质量进行评估",{"key":23,"text":24,"correct":18},"D","在施工过程中及时发现施工工艺规程是否满足设计要求和合同规定",{"key":26,"text":27,"correct":18},"E","将取得的质量数据和承包商履行职责的程序，与国家有关规范、技术标准、规定进行比较，并做出评判","BCDE","考点:质量控制。在项目施工阶段，质量控制的任务主要是在施工过程中及时检查施工工艺规程是否满足设计要求和合同规定，对所选用的材料和设备进行质量评价、对整个施工过程中的工程质量进行评估，将取得的质量数据和承包商履行职责的程序，与国家有关规范、技术标准、规定进行比较，并做出评判。",{"id":6,"name":31,"category":32,"favorite":33},"开发经营与管理","职业资格",0]