[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-349482":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},349482,141,1,"单选题","某市2016年新开工的房屋建筑面积为60万m2，2015年未完工转入今年继续施工的房屋建筑面积为20万m2，今年竣工的房屋建筑面积为80万m2。那么，该市房屋的平均建设周期为（ ）年。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",true,{"key":16,"text":17,"correct":18},"B","1.5",false,{"key":20,"text":21,"correct":18},"C","2",{"key":23,"text":24,"correct":18},"D","3","本题考查的是供给指标。平均建设周期是指某种类型的房地产开发项目从开工到竣工交付使用所占用的时间长度。在数值上，平均建设周期＝房屋施工面积\u002F新竣工面积，即平均建设周期＝（60＋20）÷80＝1（年）。",{"id":6,"name":27,"category":28,"favorite":29},"开发经营与管理","职业资格",0]