[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-349343":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},349343,141,1,"单选题","房地产开发项目的开发期，由（ ）两个阶段组成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建造期与经营期",false,{"key":16,"text":17,"correct":14},"B","准备期与经营期",{"key":19,"text":20,"correct":21},"C","准备期和建造期",true,{"key":23,"text":24,"correct":14},"D","建造期和经营准备期","本题考查的是房地产开发项目的主要不确定性因素。房地产开发项目的开发期，由准备期和建造期两个阶段组成。",{"id":6,"name":27,"category":28,"favorite":29},"开发经营与管理","职业资格",0]