[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-349311":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},349311,141,1,"单选题","动态投资回收期是反映（ ）的重要指标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","开发项目投资成本大小",false,{"key":16,"text":17,"correct":18},"B","开发项目投资回收能力",true,{"key":20,"text":21,"correct":14},"C","开发项目资金流动速度",{"key":23,"text":24,"correct":14},"D","开发项目资金实力","本题考查的是动态投资回收期。动态投资回收期，是指当考虑现金流折现时，项目以净收益抵偿全部投资所需的时间，是反映开发项目投资回收能力的重要指标。",{"id":6,"name":27,"category":28,"favorite":29},"开发经营与管理","职业资格",0]