[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-348974":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},348974,141,1,"单选题","在开发项目财务评价中，静态投资回收期肯定小于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","基准回收期",false,{"key":16,"text":17,"correct":14},"B","项目开发期",{"key":19,"text":20,"correct":14},"C","项目销售期",{"key":22,"text":23,"correct":24},"D","动态投资回收期",true,"考点:动态投资回收期。在考虑时间价值因素后，项目获得的净收益在价值上会逐年递减，因此，对于同一个项目，其动态投资回收期一定大于其静态投资回收期。动态投资回收期可能大于也可能小于基准回收期，而动态投资回收期与项目开发期和项目销售期没有必然联系。",{"id":6,"name":27,"category":28,"favorite":29},"开发经营与管理","职业资格",0]