[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-348967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},348967,141,1,"单选题","已知某投资项目的净现金流量如下表所示。如果投资者目标收益率为12%，求该投资项目的动态投资回收期（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3.625",false,{"key":16,"text":17,"correct":14},"B","4.2",{"key":19,"text":20,"correct":21},"C","4.84",true,{"key":23,"text":24,"correct":14},"D","5.125","考点:动态投资回收期。",{"id":6,"name":27,"category":28,"favorite":29},"开发经营与管理","职业资格",0]