[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-348878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},348878,141,1,"单选题","在正式申请竣工验收之前，开发商要对项目进行初步检查。检查后由（ ）列出质量缺陷清单。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","开发商",false,{"key":16,"text":17,"correct":14},"B","承包商",{"key":19,"text":20,"correct":21},"C","监理工程师",true,{"key":23,"text":24,"correct":14},"D","使用单位","考点:竣工验收。在正式办理竣工验收之前，开发商需要进行初步检查，根据初步检查情况，由项目的监理工程师列出需要修补的质量缺陷“清单”，这时承包商应切实落实修复这些缺陷，以便通过最终的正式验收。",{"id":6,"name":27,"category":28,"favorite":29},"开发经营与管理","职业资格",0]