[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-348871":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},348871,141,1,"单选题","制定进度计划时，从图中看不出各项工作之间的相互依赖和相互制约的关系，看不出一项工作的提前或落后对整个工期的影响程度，看不出哪些工序是关键工作，这是（ ）法的缺点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横道图",true,{"key":16,"text":17,"correct":18},"B","单代号网络图",false,{"key":20,"text":21,"correct":18},"C","双代号网络图",{"key":23,"text":24,"correct":18},"D","时标网络图","考点:进度控制。制定进度计划时，横道图的缺点是从图中看不出各项工作之间的相互依赖和相互制约的关系，看不出一项工作的提前或落后对整个工期的影响程度，看不出哪些工序是关键工作。",{"id":6,"name":27,"category":28,"favorite":29},"开发经营与管理","职业资格",0]