[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-348102":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},348102,140,3,"判断题","计算工程量，分部分项工程计算顺序可以按“先横后竖、先下后上、先右后左”计算法。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"分部分项工程计算顺序 1.按顺时针方向计算法 这种方法首先是从平面图的左上角开始，从左至右，然后再从上到下，最后转回到左上角为止，按顺时针方向依次计算工程量。 2.按“先横后竖、先上后下、先左后右”计算法 这种方法是从平面图的左上角开始，按“先横后竖、先上后下、先左后右”的顺序计算工程量。",{"id":6,"name":21,"category":22,"favorite":23},"基本制度与政策（含相关知识）","职业资格",0]