[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-347936":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},347936,140,3,"判断题","某建设项目的建设工期不足一年，则申领施工许可证时要求其到位资金原则上不得少于工程合同价的50％。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"建设资金已经落实。建设工期不足一年的，到位资金原则上不得少于工程合同价的50%，建设工期超过一年的，到位资金原则上不得少于工程合同价的30%。建设单位应当提供本单位截至申请之日无拖欠工程款情形的承诺书或者能够表明其无拖欠工程款情形的其他材料，以及银行出具的到位资金证明，有条件的可以实行银行付款保函或者其他第三方担保。",{"id":6,"name":21,"category":22,"favorite":23},"基本制度与政策（含相关知识）","职业资格",0]