[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-347797":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},347797,140,2,"多选题","在合同履行过程中，经发包人同意，监理人可按合同约定的变更程序向承包人发出变更指示的情形有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","取消合同中任何一项工作",false,{"key":16,"text":17,"correct":18},"B","改变合同中任何一项工作的质量或其他特性",true,{"key":20,"text":21,"correct":18},"C","改变合同工程的基线.标高.位置或尺寸",{"key":23,"text":24,"correct":18},"D","为完成工作需要施加的额外工作",{"key":26,"text":27,"correct":18},"E","改变合同中任何一项工作的施工时间","BCDE","本题考查的是建设项目施工阶段工程造价的计价与控制。在履行合同中发生以下情形之一的，经发包人同意，监理人可按合同约定的变更程序向承包人发出变更指示：（1）取消合同中任何一项工作，但被取消的工作不能转由发包人或其他人实施；（2）改变合同中任何一项工作的质量或其他特性；（3）改变合同工程的基线、标高、位置或尺寸；（4）改变合同中任何一项工作的施工时间或改变已批准的施工工艺或顺序；（5）为完成工作需要施加的额外工作。",{"id":6,"name":31,"category":32,"favorite":33},"基本制度与政策（含相关知识）","职业资格",0]