[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-347794":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},347794,140,2,"多选题","工程量清单计价中的分部分项工程采用综合单价，由（ ）组成。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","规费",false,{"key":16,"text":17,"correct":18},"B","人工费.材料费",true,{"key":20,"text":21,"correct":18},"C","企业管理费",{"key":23,"text":24,"correct":18},"D","利润及一定范围的风险费用",{"key":26,"text":27,"correct":18},"E","施工机具使用费","BCDE","本题考查的是工程量清单计价法。综合单价包括人工费、材料费、施工机具使用费、企业管理费和利润以及一定范围的风险费用。",{"id":6,"name":31,"category":32,"favorite":33},"基本制度与政策（含相关知识）","职业资格",0]