[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-347786":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},347786,140,2,"多选题","措施项目费的内容包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","安全文明施工费",true,{"key":16,"text":17,"correct":14},"B","夜间施工增加费",{"key":19,"text":20,"correct":14},"C","二次搬运费",{"key":22,"text":23,"correct":14},"D","冬雨季施工增加费",{"key":25,"text":26,"correct":27},"E","社会保险费",false,"ABCD","本题考查的是建筑安装工程费用的构成。措施项目费是指为完成建设工程施工，发生于该工程施工前和施工过程中的技术、生活、安全、环境保护等方面的费用，包括安全文明施工费、夜间施工增加费、二次搬运费、冬雨季施工增加费、已完工程及设备保护费、工程定位复测费、特殊地区施工增加费、大型机械设备进出场及安拆费以及脚手架工程费等。选项E，属于规费。",{"id":6,"name":31,"category":32,"favorite":33},"基本制度与政策（含相关知识）","职业资格",0]