[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-347783":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},347783,140,2,"多选题","下列关于定额计价方式与工程量清单计价方式的区别与联系的表述中，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","主要计价依据及其性质不同",true,{"key":16,"text":17,"correct":14},"B","单价与报价的组成不同",{"key":19,"text":20,"correct":21},"C","编制工程量的主体相同",false,{"key":23,"text":24,"correct":21},"D","适用阶段相同",{"key":26,"text":27,"correct":14},"E","是否区分施工实体性损耗和施工措施性损耗不同","ABE","本题考查的是定额计价方式与工程量清单计价方式的差别。定额计价方式与工程量清单计价方式的差别主要表现在以下几个方面：（1）体现我国建设市场发展过程的不同定价阶段；（2）主要计价依据及其性质不同；（3）编制工程量的主体不同；（4）单价与报价的组成不同；（5）适用阶段不同；（6）合同价格的调整方式不同；（7）是否区分施工实体性损耗和施工措施性损耗不同。",{"id":6,"name":31,"category":32,"favorite":33},"基本制度与政策（含相关知识）","职业资格",0]