[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-347230":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},347230,140,2,"多选题","工程建设监理的基本方式是控制，其中的“三控”工作是指工程( )控制。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进度",true,{"key":16,"text":17,"correct":18},"B","人员",false,{"key":20,"text":21,"correct":14},"C","质量",{"key":23,"text":24,"correct":18},"D","安全",{"key":26,"text":27,"correct":14},"E","投资","ACE","监理的基本方法就是控制，基本工作是“三控”、“两管”、“一协调”。 “三控”是指监理工程师在工程建设全过程中的工程进度控制、工程质量控制和工程投资控制； “两管”是指监理活动中的合同管理和信息管理； “一协调”是指全面的组织协调。",{"id":6,"name":31,"category":32,"favorite":33},"基本制度与政策（含相关知识）","职业资格",0]