[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-346992":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},346992,140,1,"单选题","从工程费用计算角度，工程计价的顺序一般为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","单位工程总价→分部分项工程单价→工程项目总价→建设项目总造价",false,{"key":16,"text":17,"correct":18},"B","分部分项工程单价→单位工程总价→工程项目总价→建设项目总造价",true,{"key":20,"text":21,"correct":14},"C","分部分项工程单价→单位工程总价→建设项目总造价→工程项目总价",{"key":23,"text":24,"correct":14},"D","分部分项工程单价→工程项目总价→单位工程总价→建设项目总造价","本题考查的是工程造价计价的基本原理。从工程费用计算角度，工程计价的顺序一般为：分部分项工程单价→单位工程总价→工程项目总价→建设项目总造价。",{"id":6,"name":27,"category":28,"favorite":29},"基本制度与政策（含相关知识）","职业资格",0]