[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-346980":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},346980,140,1,"单选题","监理人收到承包人变更报价书后的（ ）天内，根据变更估价原则，商定或确定变更价格。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7天",false,{"key":16,"text":17,"correct":18},"B","14天",true,{"key":20,"text":21,"correct":14},"C","21天",{"key":23,"text":24,"correct":14},"D","28天","本题考查的是建设项目施工阶段工程造价的计价与控制。监理人收到承包人变更报价书后的14天内，根据变更估价原则，商定或确定变更价格。",{"id":6,"name":27,"category":28,"favorite":29},"基本制度与政策（含相关知识）","职业资格",0]