[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-346488":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},346488,140,1,"单选题","(2016真题) 针对在项目实施过程中可能发生难以预料的支出，需要事先预留的工程造价部分是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂定金额",false,{"key":16,"text":17,"correct":18},"B","基本预备费",true,{"key":20,"text":21,"correct":14},"C","价差预备费",{"key":23,"text":24,"correct":14},"D","工程建设其他费用","本题考查的是工程造价的构成。基本预备费是针对在项目实施过程中可能发生难以预料的支出，需要事先预留的费用，又称工程建设不可预见费用。BC都是预备费。但是引起的原因不同。C是价格变化引起的。",{"id":6,"name":27,"category":28,"favorite":29},"基本制度与政策（含相关知识）","职业资格",0]