[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-346410":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},346410,140,1,"单选题","(2011真题) 建设工程施工和施工管理的最后环节是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工验收",true,{"key":16,"text":17,"correct":18},"B","竣工决算",false,{"key":20,"text":21,"correct":18},"C","质量保修项目维修",{"key":23,"text":24,"correct":18},"D","交付使用","本题考查的是建设工程的竣工验收管理制度。竣工验收是建设工程施工和施工管理的最后环节。",{"id":6,"name":27,"category":28,"favorite":29},"基本制度与政策（含相关知识）","职业资格",0]