[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-346124":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},346124,140,1,"单选题","针对在项目实施过程中可能发生难以预料的支出，需要事先预留的工程造价部分是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂定金额",false,{"key":16,"text":17,"correct":18},"B","基本预备费",true,{"key":20,"text":21,"correct":14},"C","涨价预备费",{"key":23,"text":24,"correct":14},"D","工程建设其他费用","基本预备费——是针对在项目实施过程中可能发生难以预料的支出，需要事先预留的费用，又称工程建设不可预见费用。主要是指设计变更及施工过程中可能增加工程量的费用。",{"id":6,"name":27,"category":28,"favorite":29},"基本制度与政策（含相关知识）","职业资格",0]