[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-346118":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},346118,140,1,"单选题","某建设项目设备及工器具购置费用2000万元。建筑安装工程费用5000万元，工程建设其他费用3000万元，预计建设期为3年，年均价格上涨率为3％。基本预备费率5％，则基本预备费为( )万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","500",true,{"key":16,"text":17,"correct":18},"B","815",false,{"key":20,"text":21,"correct":18},"C","1445",{"key":23,"text":24,"correct":18},"D","1473","工程费用是指直接构成固定资产实体的各种费用，可以分为设备及工器具购置费和建筑安装工程费；基本预备费＝(工程费用＋工程建设其他费用)×基本预备费率=(设备及工器具购置费+建筑安装工程费用+工程建设其他费用)×基本预备费率＝(2000+5000+3000)×5％=500万元。",{"id":6,"name":27,"category":28,"favorite":29},"基本制度与政策（含相关知识）","职业资格",0]