[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-345837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},345837,140,1,"单选题","建设单位领取施工许可证后，因故不能按期开工，可申请延期，延期（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以一次为限，不超过3个月",false,{"key":16,"text":17,"correct":14},"B","以一次为限，不超过6个月",{"key":19,"text":20,"correct":21},"C","以两次为限，每次不超过3个月",true,{"key":23,"text":24,"correct":14},"D","以两次为限，每次不超过6个月","本题考查的是施工许可管理。建设单位应当自领取施工许可证之日起3个月内开工。因故不能按期开工的应当在期满前向发证机关申请延期，并说明理由；延期以两次为限，每次不超过3个月。",{"id":6,"name":27,"category":28,"favorite":29},"基本制度与政策（含相关知识）","职业资格",0]