[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-345828":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},345828,140,1,"单选题","关于建筑工程施工许可证管理的说法，错误的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工许可证应当放置在施工现场备查",false,{"key":16,"text":17,"correct":14},"B","施工许可证不得涂改",{"key":19,"text":20,"correct":14},"C","建设单位应当自领取施工许可证之日起3 个月内施工",{"key":22,"text":23,"correct":24},"D","施工许可证不能延期",true,"施工许可证分为正本和副本，正本和副本具有同等法律效力。复印的施工许可证无效。施工许可证应当放置在施工现场备查，并按规定在施工现场公开。施工许可证不得伪造和涂改。建设单位应当自领取施工许可证之日起3 个月内开工。因故不能按期开工的，应当在期满前向发证机关申请延期，并说明理由；延期以两次为限，每次不超过3 个月。既不开工又不申请延期或者超过延期次数、时限的，施工许可证自行废止。",{"id":6,"name":27,"category":28,"favorite":29},"基本制度与政策（含相关知识）","职业资格",0]