[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-345827":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},345827,140,1,"单选题","因故不能按期开工的建设单位，应当在施工许可证期满前向发证机关申请延期，并说明理由；延期以两次为限，每次不超过( )个月。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","4","建设单位应当自领取施工许可证之日起3 个月内开工。因故不能按期开工的，应当在期满前向发证机关申请延期，并说明理由；延期以两次为限，每次不超过3 个月。既不开工又不申请延期或者超过延期次数、时限的，施工许可证自行废止。",{"id":6,"name":27,"category":28,"favorite":29},"基本制度与政策（含相关知识）","职业资格",0]