[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-327199":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},327199,113,1,"单选题","《安全生产法》明确了建设项目“三同时”准备阶段相关单位的职责。建设项目施工期间，应由（ ）对安全设施的工程质量负责。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计单位",true,{"key":16,"text":17,"correct":18},"B","安全评价机构",false,{"key":20,"text":21,"correct":18},"C","施工单位",{"key":23,"text":24,"correct":18},"D","安全生产监督管理部门","",{"id":6,"name":27,"category":28,"favorite":29},"安全生产管理","职业资格",0]