[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-273377":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},273377,102,1,"单选题","从事境外工程总承包的中国企业在投标欧洲某个电网建设工程后，在未确定是否中标之前，最适合利用（ ）来管理汇率风险。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人民币／欧元期权",true,{"key":16,"text":17,"correct":18},"B","人民币／欧元远期",false,{"key":20,"text":21,"correct":18},"C","人民币／欧元期货",{"key":23,"text":24,"correct":18},"D","人民币／欧元互换","本题中，一旦企业中标，前期需投入欧元外汇，为规避欧元对人民币升值的风险，企业有两种方案可供选择：一是卖出人民币／欧元期货；二是买人人民币／欧元看跌期权。第一种方案利用外汇期货市场，价格灵活，操作简单。但是利用外汇期货无法管理未中标风险，因此对于前期需投入的欧元的汇率风险不能完全规避。第二种方案中，外汇期权多头只要付出一定的权利金，就能获得远期以执行价格的汇率来买卖外汇的权利。因此，除了能够规避欧元／人民币汇率波动风险外，也能够规避未来不能中标的风险。",{"id":6,"name":27,"category":28,"favorite":29},"期货投资分析","经济金融",0]